August A 1869 m² plant setted up at No.96, Gaoping Rd., Yangmei City, Taoyuan County 326, Taiwan (R.O.C.) |
||||||||||
August An extrusion press 4"(690US TON) was setted up, production started |
|||||||||||
November An extrusion press 5.5"(1100US TON) was setted up to improve production capacity |
|||||||||||
December Accredited with ISO 9001 Quality Management Standard (QMS) |
|||||||||||
March Another extrusion press 4"(690US TON) was setted up, production capacity up to 800 tons |
|||||||||||
June The purchase of sawing machine. The production of Aluminium doors&windows started |
|||||||||||
June Setted up wind and rain resistant mock up test equipment to improve quality. |
|||||||||||
July New 5000m² plant setted up |
|||||||||||
March The purchase of 10" (3000US TON) extrusion press,production of Aluminium curtain wall started |